CITY OF MALOLOS, Bulacan — NLEX Corporation announces that all of the four lanes of Marilao Northbound are now passable to vehicles since 1 a.m. of March 26, 2025 (Wednesday), ahead of the projected schedule.
While all lanes are now passable, supporting steel poles will remain on the lanes to allow concrete curing of the bridge. With this development, traffic flow in Marilao Northbound is expected to improve and normalize in the next few days.
On March 19, the Marilao Bridge sustained damage from a truck violating regulations, causing traffic flow changes to facilitate ongoing repairs and ensure motorists’ safety.
Originally scheduled for completion in two weeks, NLEX accelerated the repairs, with teams working around the clock and with the expedited delivery of the fabricated steel needed for the bridge.
We thank the motoring public for their utmost understanding and patience while repairs were ongoing.
Rest assured that NLEX continues to intensify safety and traffic measures in key areas of the expressway to ensure the safety and convenience of our valued customers. (UnliNews Online)